2019 - Renovations

Sept. 13, 2019

West Union after bond construction:

Photo 1: a new, secured entry is locked during the school day. Visitors and late students will be required to check into the main office.

new, secured entry

Photo 2: the elevator has been installed, providing ADA access between the lower and upper floors.

new elevator

Photo 3: framing and finishing behind the elevator on the lower floor produced a new SLC office.

new SLC office

Photo 4: fencing now surrounds the perimeter of the school play area and grounds.

fencing

Photo 5: neat lines of conduit and fresh paint cover up the wiring, ductwork and seismic upgrades that went in the ceiling and behind the walls. The white beams in the middle of the hallway will be painted and decorated shortly.

hallway

Photo 1: an elevator is being installed to improve ADA access.

elevator installation

Photo 2: new HVAC units are being installed throughout the building.

new HVAC unit in library

Photo 3: a crew members works on replacing domestic water pipe and lines.

replacing domestic water pipe

Photo 4: bracing in the walls of classrooms will bring them up to the "safe exit" seismic standard.

seismic bracing in classroom

Photo 5: the parking lot is being restriped.

restriping the parking lot

Photo 1: the gym is undergoing seismic reinforcement to meet updated code requirements.

seismic reinforcement in gym

Photo 2: a pad area for electric utility connections is being constructed at the northeast edge of the building.

electric utility pad construction

Photo 3: new ventilation ducts have been installed in classrooms.

ventilation ducts in a classroom

Photo 4: bricks await installation in the bottom floor of the building, as mortar is mixed outside.

bricks and mortar-mixing equipment

Photos 1 and 2: The building is undergoing roofing and seismic upgrades.

Rooftop work

Seismic upgrade in classroom

Photos 3 and 4: Upgraded HVAC will add air conditioning to classrooms and the rest of the building.

HVAC ductwork in classroom

New HVAC ducts in classroom ceiling

Photo 5: A new elevator will enhance ADA accessibility between floors.

Pre-construction of elevator area

Photo 6: A newly-poured concrete walkway provides better accessibility between the playgrounds and building.

Paved walkway between playgrounds

Milestones

June 17, 2019 - abatement and other preparatory work begins.