Project Scope

aerial of WL Henry campus

construction timeline for WL Henry

 


Please note that project renderings, costs and schedules may change due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Total costs: $11.7 million

COMPLETED

  • Fence/Gate Updates

As added scope in summer 2022, fencing and gates updates were made in the kinder and gym areas for security and to facilitate exit in case of emergency.

  • Security Upgrades

In spring 2021, after completion of the gym, W.L. Henry's existing security systems were upgraded with such measures as security cameras, interior door locks, and alert/warning systems.

  • Replace Covered Play Posts

Some of the posts in the covered play structure were found to have weakened; these were replaced in spring 2021.

  • New Gym

An exciting addition to the campus is a new gymnasium that enables dedicated use for PE and activities, separate from the cafeteria, and which can serve as an emergency shelter for the community in case of a major earthquake. Construction was completed in March 2021; watch the virtual tour.

  • Building Improvements

During the summer of 2020, the existing building underwent renovations that included seismic, HVAC and roofing upgrades.

  • Parent/Bus Dropoff Areas

From June to August 2020, the parent/bus dropoff areas was modified to separate personal vehicles from buses, not only enhancing pedestrian and driver safety, but allowing for a smoother flow of traffic during dropoff and pickup times.

  • Flexible Furniture

New flexible furniture (FFE) was delivered to W.L. Henry classrooms in summer 2019. Research has shown the furniture to promote engagement and learning.

  • Playground

W.L. Henry's playground was installed on a safer, rubberized tile surface in summer 2018, and students can now play rain or shine on a new, synthetic turf area.

  • Modular Building

Due to permitting delays, W.L. Henry's new modular building, originally scheduled for summer 2018, was installed in November 2018. The permanent building houses three classrooms and includes a bathroom facility. The modular replaces the temporary, two-classroom, no-bathroom portable, which was demolished on March 23, 2018.

Project Manager

Cornerstone Management Group

  • Modular building, playground: Rick Cunningham
  • Gym/renovations: Rick Cunningham
  • Entry vestibule*: John Abel

Architects/Engineers

  • Modular building, playground: 3J Consulting, Inc.
  • Gym: Mahlum Architects
  • Entry vestibule*: Process-PDX

Contractors

  • Modular building: Five Star Builders
  • Playground
    • Site work: Five Star Builders, Inc.
    • Structure: Cascade Recreation
    • Rubber tile: NW Playground Equipment
  • Gym/renovations: Emerick Construction
  • Entry vestibule*: Inline Construction

 

*grouped with Indian Hills, Minter Bridge, and Tobias entry vestibule projects