2018-19 - Playground & Modular
March 29, 2019
The space where an old portable was recently demolished and removed is being repaved to provide additional parking space/hardscape at the back of the school.
An old portable, at the end of its life, is demolished to make way for an asphalt-paved area. Students who were formerly housed in the portable are now in the new modular building, which opened in January.
W.L. Henry Elementary sixth-graders entered their new classrooms in the modular building constructed through the 2017 HSD Bond.
Los estudiantes de sexto grado de W.L. Henry entraron a sus nuevos salones de clases en el edificio modular construido mediante el bono 2017 de HSD.
Utility connections and the entry walkway have been completed, and the modular building will be ready for students when they return from winter break.
Crews connect a sewer line from W.L. Henry's new modular to the main pipe across the field. Water and electrical connections have been completed. The floor will be worked on next Tuesday, Dec. 11, and the building is expected to be ready for students to move into their classrooms after winter break.
- New Modular Building Installation
The old portable has been replaced with a permanent modular building housing three classrooms and restroom.
- Playground is Popular
Students are enjoying their new play structure, swings and play area.
Synthetic turf is being laid onto the play area. After some heating and settling, the turf will be cut to shape, stretched across the surface, and tacked into place.
The concrete base for the playground's rubberized tiles has been installed. Water sprinklers are run to allow the concrete to cure evenly in the extreme heat. The holes are where the posts of the play structure will be placed.
Poles from the existing play structure remain standing as the play area is prepared for a concrete base, on which rubberized tiles will be laid.
Milestones
March 23, 2019 - the old portable is demolished and crews prepare the site for paving.
Jan. 7, 2019 - the modular is opened to students.
Nov. 2, 2018 - installation of the new modular building has begun.
Aug. 31, 2018 - the playground is completed and ready for students.
June 20, 2018 - installation of the new play area begins.