20220824

Photo 1: temporary shower fixtures have been installed in the locker rooms until the specified fixtures arrive after shipment delays. This will enable student-athletes to take hot showers in the meantime.

temporary shower fixtures

Photo 2: the new water heaters have both been delivered and installed in the utility room, fed by the new water pipes.

new water heaters in utiity room

Photo 3: the last bit of shrouding will be installed before the crew does the final cleanup and awaits installation of the new shower fixtures.

pipe shrouding to be installed