20200206

Photos 1-2: classrooms and the classroom hallway on the first floor have been sheetrocked.

sheetrocked classroom

sheetrocked classroom hallway

Photo 3: basketball backboards and hoops have been installed in the gym.

gym construction with basketball hoops

Photo 4: crew members are illuminated through the plastic sheeting currently on the gym windows.

crew members working on gym windows

Photo 5: a first-floor conference room ready to be painted.

nearly-finished conference room

Photos 6 and 7: ductwork installation continues on the second floor.

exposed HVAC ducts

workers cutting HVAC ducts to size

Photo 8: a crew member installs siding on the south side of the building.

installing siding on the building